Country:  Turkey
Customer:  South Stream Transport B.V.
Scope of Work: SPK-Magistral has carried out welding procedure qualification in accordance with DNV-OS-F101-2010 (Offshore Standard for Submarine Pipeline Systems) prior to production time. CRC-EVANS welding complex was used for welding of the pipeline sections installed in areas with maximum slope of 7°. Manual welding technique was used for welding of bends. The time of continuous manual welding of one joint was 22 hours. Combined argon and electric arc welding process was applied at the receiving terminal. Canusa equipment and materials were used for coating of welded joints. Total number of welded joints made by SPK-Magistral using manual welding is over 100 joints. Defective weld joints – 0.